We
are now working on week 25 of a 33 week programme.
All
windows are in place and glazing should be complete within two weeks.
Glass is being cut to size and toughened.
Plumbing
work is progressing and the boiler will be installed shortly.
Rooms
2 & 3 are looking good with plastering and flooring almost complete.
Room
1 still has the new floor to lay once the pipe work for the under
floor heating is installed.
Work
on the outside area is progressing well with the play area looking
good.
The
boundary wall will be progressed this week once the building inspectors
are happy.
The
lease with the Sunshine Play Group is now in the hands of their
solicitor.
Completion
date is now planned for week commencing the 26 th October.
The
A158 will have traffic control during the first two weeks of October
to allow the windows to be painted and the gutters to be fitted.
There will be a small amount of pointing up to do on the roadside
brickwork. This work may be completed within a week dependant on
the weather which would reduce the traffic delays. Everything is
being done to keep this disruption to a minimum.
The
official opening date will be announced in my next report.